Juan Pinos

31/03/2016 18:36:31

When I run a 1D steady simulation, the program show this error, in almost all my cross sections. I need help with the solution, please anyone who can help me!

I give an example of one of my cross sections.

PS. (The section have more points up and down, but I don't include them,  because it would be too large)

 

 

x(m) y(m) Manning n Marker Easting Northing
50.654 2230.41 0.042   746701.69 9678265.82
53.633 2230.44 0.042   746704.57 9678265.07
56.618 2230.49 0.042   746707.45 9678264.31
59.597 2230.55 0.042   746710.33 9678263.56
62.576 2230.6 0.042   746713.22 9678262.8
65.552 2230.64 0.042   746716.1 9678262.05
68.54 2230.64 0.042   746718.98 9678261.29
71.516 2230.65 0.042   746721.86 9678260.54
74.495 2230.65 0.042   746724.75 9678259.78
83.435 2230.59 0.042   746727.63 9678259.02
86.414 2230.56 0.042   746730.51 9678258.27
89.392 2230.56 0.042   746733.39 9678257.51
95.89 2230.53 0.042   746736.28 9678256.76
98.696 2230.54 0.042   746739.16 9678256
101.502 2230.54 0.042   746742.04 9678255.25
104.298 2230.53 0.035 Left 746744.92 9678254.49
107.104 2230.32 0.035   746747.81 9678253.74
108.951 2229.87 0.035   746750.69 9678252.98
110.788 2229.4 0.035   746753.57 9678252.22
112.372 2228.96 0.035   746756.45 9678251.47
113.946 2228.55 0.035   746759.34 9678250.71
116.77 2227.67 0.035   746762.22 9678249.96
119.323 2226.97 0.035   746765.1 9678249.2
129.806 2226.97 0.035   746767.99 9678248.45
132.108 2226.98 0.035   746770.87 9678247.69
169.667 2226.98 0.035   746773.75 9678246.94
172.189 2227.03 0.035   746776.63 9678246.18
175.164 2228.28 0.035   746779.51 9678245.42
177.646 2230.11 0.035   746781.66 9678245.13
180.131 2230.569 0.035 Right 746783.8 9678244.84
185.072 2230.28 0.051   746785.95 9678244.55
186.606 2230.33 0.051   746788.73 9678244.17
187.486 2230.41 0.051   746791.51 9678243.79
189.026 2230.53 0.051   746794.28 9678243.41
190.416 2230.58 0.051   746797.06 9678243.03
191.496 2230.6 0.051   746798.89 9678242.78
192.766 2230.63 0.051   746800.71 9678242.53
194.086 2230.66 0.051   746802.28 9678242.32
195.476 2230.67 0.051   746803.84 9678242.11
196.886 2230.66 0.051   746806.64 9678242.48
197.562 2230.64 0.051   746809.18 9678242.73
198.296 2230.63 0.051   746811.17 9678242.94
199.03 2230.54 0.051   746813.17 9678243.14
199.765 2230.45 0.051   746815.32 9678243.35
200.5 2230.36 0.051   746817.47 9678243.57

Konrad

Flood Modeller Support

01/04/2016 08:23:26

Best answer

  1. Note that this a warning/advisory as opposed to an error - the model will still run beyond this.
  2. It will go away if you add a Panel marker (the check box in the middle) when your Manning's n values change, i.e. same line as your Left bank marker; one below the Right bank marker.

This splits the section up into three vertical panels, where the conveyance is calculated separately for each, and then summed to give a total section conveyance. Primarily this is to stop a kink, and hence potential instabiliities, in the conveyance-stage relationship when the water goes out of bank (when the section slope changes from being nearly vertical to nearly horizontal), and therefore usually coincident with a change in roughness value.

The Help page quotes:

"different values ( /- 20 %) for Mannings n encountered within one panel

Differing values of Manning's n (of over 20%) have been entered within the same panel. You are normally advised to insert panel markers when the Manning's value changes. Note that panel markers may not appear within bridge arches."